Shilpis work
Datta Hanuman ki Jai!

 Karya Siddhi Hanuman ki Jai!

 

 

Work did slow down due to heavy rains and some very low temperatures.

Indianization team continue building molds needed for inner shrines, sculptures and decorative idols.

AUI construction company laid down the roof for the new temple building.

AUI continued laying down the infra structure to the new building like sprinkler systems, Electrical and Plumbing work.

Insulation materials, AC unit curbs did arrive.

All this time, inspections were conducted by Frisco City and ‘Alpha testing’.

Shrine Concrete work is being done by an independent contractor. He has finished re baring the five shrines. Concrete pour expected next week.

Planning is in progress to build scaffolding and a track on the roof to take the granite stones.

Please tune in for more updates next month.