New Temple Construction Details & Updates
Jun
15

2014-Jun : Pillars and Inner Shrine Moulds

Datta Hanuman ki Jai! Temple construction is actively progressing.  work related Concrete pouring for  pillars have began. Please click on the link below to look at more pictures of construction and also shilpis work on inner shrine moulds. https://www.flickr.com/photos/hanumantemple/sets/72157646255622624/ Karya Siddhi Hanuman ki Jai!

May
21

2014-May: Shilpis working on Inner Shrines

Datta Hanuman ki Jai! Shilpis have started working on building the needed mold for inner shrines.  Click on the following link to see more pictures of shilpis working on inner shrines. https://www.flickr.com/photos/hanumantemple/sets/72157646255622624/ Karya Siddhi Hanuman ki Jai!

May
7

2014-Apr: Shilpis from India Arrived

Datta Hanuman ki Jai! Shilpis from India have arrived. They have started working on creating molds needed for inner shrines. Click This for more pictures of shiplis working. Karya Siddhi Hanuman ki Jai! 

May
7

2014-Mar: Foundation in Progress

Datta Hanuman ki Jai! Temple foundation in progress. Click This Link   for more pictures. Temple team developed a video about the construction progress. Please click this link to see it: http://vimeo.com/92237354 Karya Siddhi Hanuman ki Jai!  

Feb
24

2014-Feb: Drilling & Pouring Concrete Piers

Datta Hanuman ki Jai! Drilling & Pouring concrete Piers for foundations Drilling and Pouring concrete for Foundation Piers is complete. Click this link to view more pictures of Temple construction and progress. Guaranteed Maximum Price (GMP) is in progress.  After multiple iterations and…

Feb
23

2014-Feb: Building Site Permit Approved

Datta Hanuman ki Jai! Progress Update: Frisco City has approved the Building site permit. Attached are some pictures of the work being done on inner shrine by shilpis (master sculptors) in Benguluru, India. The stone work will need to be shipped to Frisco…

Jan
14

2014-Jan: High Level Construction Schedule Received

Datta Hanuman ki Jai! Progress Update: The Marakata KSHT construction review team met frequently this past two weeks to review the GMP of the temple. High level project plan from AUI contractors had been published. A tracking level project plan was requested from…

Dec
30

2013-Dec: Utilities Progress

Datta Hanuman ki Jai! Progress Update: The Temple land, east of the old gravel parking lot, has been plowed and utility lines are being laid.  View the attached pictures (below) to see the construction in action in preparation for the future Temple. The Marakata…

Nov
20

Navaratri Sarees for 8sq.ft Sponsors

Special for NEW 8 sqft sponsorships For new 8sqft sponsorhsips only. Offer a BRICK for the new Temple building. Donor’s name will be recognized in the new Temple. Sponsor may choose one of the special Devi Navaratri sarees to take home as prasad. Please note: Devi sarees…

Nov
8

2013-Nov: Digging for Utilities

Datta Hanuman Ki Jai !! During November, digging started in order to lay down utilities for the new Temple. The following activities were executed: Sewer Line Water Line Convert inlet to manhole  . Move job trailer. Cut grade for detention pond. Demo concrete…